Awarding agency: Department of Energy
Who got paid, how much, for what, and whether it is defensible. Citizen opinion on the record, not a mandate.
Status and record
THE PURPOSE OF THIS ACTION IS TO AWARD THE ICP TEN YEAR PLAN HYBRID TASK ORDER UNDER SINGLE AWARD MASTER IDIQ CONTRACT 89303321DEM000061. CLIN 05 S1W D&D IS INCLUDED WITH AUTHORIZATION TO COMMENCE SCOPE 10/1/2023.
$1.6B · DELIVERY ORDER · Department of Energy · ID
FEDERAL SPENDING · CITIZEN OPINION
Was this federal payment to IDAHO ENVIRONMENTAL COALITION LLC worth it?
$1.6B · Department of Energy to IDAHO ENVIRONMENTAL COALITION LLC
Be the first to put your opinion on the record.
What this award is
AI analysis
This is an 8-year contract worth $1.6 billion awarded by the Department of Energy (DOE) to Idaho Environmental Coalition LLC to carry out a cleanup plan at the Idaho Cleanup Project (ICP) site. The company will manage and perform demolition and decommissioning (D&D) work, which means safely shutting down and cleaning up old nuclear facilities.
DEEPER CONTEXTAnalysis · Risks · Arguments
WHY THIS MONEY IS BEING SPENT
WHY WAS THIS FUNDED?
The DOE is required by federal law and agreements with the state of Idaho to clean up radioactive and hazardous waste left over from decades of nuclear energy and weapons research. This contract was issued under a pre-established master contract (number 89303321DEM000061) that allows the government to assign large, long-term cleanup tasks.
WHAT PUBLIC PROBLEM IS IT TRYING TO SOLVE?
The Idaho National Laboratory site contains radioactive waste and contaminated facilities from past nuclear research and weapons production. If left unaddressed, this contamination poses risks to groundwater, the environment, and public health in the surrounding region.
WHO BENEFITS?
Residents of Idaho, particularly those near the cleanup site, benefit from reduced environmental and health risks. Workers in the nuclear cleanup industry are employed, and the state of Idaho benefits from the fulfillment of cleanup commitments made by the federal government.
Plain-language reading generated from the USASpending award record. Not legal or financial advice.
RISKS AND TRADEOFFS
WHAT ARE THE RISKS?
A contract of this size and duration carries risks of cost overruns, schedule delays, and challenges in overseeing complex nuclear cleanup work over eight years. Accountability depends on strong federal oversight to ensure the work is completed safely, on time, and within budget.
WHAT HAPPENS IF FUNDING IS REMOVED?
Without this contract, radioactive and hazardous waste at the Idaho site would remain unaddressed, potentially violating federal agreements with the state of Idaho and leaving contamination that could threaten local groundwater and the environment.
FOR AND AGAINST
ARGUMENTS FOR
- •Cleaning up nuclear waste protects the health of Idaho residents and preserves the quality of the regional water supply for current and future generations.
- •The federal government has existing legal obligations to clean up this site, so this contract fulfills commitments already made to the state of Idaho.
- •Long-term cleanup contracts provide stable employment for skilled workers in the nuclear decommissioning field.
ARGUMENTS AGAINST
- •A single-award contract worth $1.6 billion over eight years limits competition, which could reduce pressure on the contractor to control costs or maximize efficiency.
- •Large, long-term nuclear cleanup projects have a well-documented history of cost overruns and delays across the DOE complex, raising concerns about whether the final price tag will stay within the awarded amount.
- •Some critics argue that funds of this scale could be better managed through smaller, more competitive contracts that are easier to monitor and adjust over time.
SPENDING TIMELINE
Add a tag
Written opinion on whether this spending is appropriate · not a duplicate of the Worth It / Wasteful vote or spending record. Similar opinions on this spending record can open a solution poll.
3 similar opinions open a solution poll
Loading opinions
Your stance is citizen opinion; it does not form a citizen mandate. Mandate accountability applies when Congress votes on tracked legislation.